Milestones |
|
 |
|
| |
|
|
| 2007 |
|
|
Commissioning of Line
V in April 2007, capacity increases to 285,000 mt
per annum, to become the largest Carbon Black by
a plant at a single location |
| 2004 |
|
|
Commissioning of Line-IV,
capacity increases to 200,000 MTPA, to become the
world's largest Carbon Black plant at a single location. |
| 2001 |
|
|
Debottlenecking and
Oxygen Enrichment, capacity increases to 137,000
mtpa |
| 1999 |
|
|
Commissioning of Line-III,
capacity increases to 110,000 mtpa |
| 1997 |
|
|
Commissioning of Line-II,
capacity increases to 70,000 mtpa |
| 1995 |
|
|
Addition of new reactor
in Line-I, capacity increases to 35,000 mtpa |
| 1994 |
|
|
Commencement of operations
by setting up a single line with production capacity
of 20000 mtpa |

|
|
| 2007 |
|
|
Commissioning of Line
III at Gummidipoondi in June 2007, total capacity
increases to 240,000 mt per annum |
| 2005 |
|
|
Debottlenecking at both
locations, capacity increases to 170,000 mtpa |
| 2004 |
|
|
Commissioning of Line-II
at Gummidipoondi, total capacity increases to 160,000
mtpa |
| 2000 |
|
|
Debottlenecking at
both locations, capacity increases to 110,000 mtpa |
| 1998 |
|
|
New plant commissioned
at Gummidipoondi, near Chennai. Total capacity increases
to 95,000 mtpa |
| 1993 |
|
|
Commissioning of Line-II
at Renukoot, capacity increases to 60,000 mtpa |
| 1992 |
|
|
Debottlenecking at
Renukoot, capacity increases to 30,000 mtpa |
| 1988 |
|
|
Commencement of operations
by setting up a single line at Renukoot of production
capacity 20,000 mtpa |
| 1987 |
|
|
Technology from Philips
Petroleum, USA used for setting up operations in
Renukoot |

|
|
| 2005 |
|
|
Commissioning of Line-II,
capacity increases to 50,000 mtpa |
| 2004 |
|
|
Line-I modification,
capacity increases to 15,000 mtpa |
| 2003 |
|
|
Commencement of operations
with production capacity of 12,000 mtpa |
| 2002 |
|
|
Initial MoU |

|
|
| 2005 |
|
|
Commissioning of Line-V,
capacity increases to 210,000 mtpa |
| 2004 |
|
|
De-bottlenecking, capacity
increases to 160,000 mtpa |
| 1996 |
|
|
Commissioning of Line-IV,
capacity increases to 140,000 mtpa |
| 1995 |
|
|
Commissioning of Line-III,
capacity increases to 105,000 mtpa |
| 1990 |
|
|
Commissioning of Line-II,
capacity increases to 65,000 mtpa |
| 1986 |
|
|
De-bottlenecking, capacity
increases to 34,000 mtpa |
| 1980 |
|
|
Commencement of operations
with production capacity of 16,000 mtpa |

|
|
|
|
|
|
|